In 2004, China witnessed the launch, construction and initial
operation of many major investment projects. In late December,
China Investment published its list of the nation's top
ten projects for the year.
1. Yichang-Wanzhou Railway Breaks Ground
Construction began in February of the long-awaited railway
linking Yichang, in east China's Hubei
Province, and Wanzhou, near Chongqing Municipality in the
southwest. It is the most challenging mountain railway ever
constructed, and will cost 17 billion yuan (US$2.1 billion).
The 378-kilometer line will pass through Yidu, Changyang,
Badong, Jianshi, Enshi and Lichuan on its way to Wanzhou. It will
also encounter underground lakes, caves and landslide and fault
zones along 70 percent of the route.
It will have the highest number of bridges (183) and tunnels
(114) in China, accounting for 71 percent of its total length. More
than half of the line's 24 stops will be built on bridges and the
remainder will be in tunnels.
The railway also sets a record in construction cost at 45
million yuan (US$5.4 million) per kilometer. In contrast, the
Jitong Railway, which traverses the Inner Mongolia Autonomous
Region and was completed in 1995, cost about 19 million yuan
(US$2.3 million) per kilometer to build.
2. China's First Coal-to-liquid-fuel Plant Gets Green
Light in Shaanxi
In March, the country's first coal-to-liquid-fuel plant got the
green light for construction in Shenmu County, western China's
Shaanxi Province. Investment in the plant will total 200 billion
yuan (US$24.2 billion), with 30 billion yuan (US$3.6 billion)
budgeted for Phase One. When completed, the plant is expected to
have an annual production capacity of 20 million tons of
clean-burning, finished fuel products.
The plant uses a process in which steam and oxygen are passed
over coke at high temperatures and pressures, producing hydrogen
and carbon monoxide, which are then reassembled into liquid fuels.
Sulfur and other pollutants such as ash and mercury are removed,
producing gasoline and diesel that are high grade and clean.
The China Shenhua Coal-to-Liquid-Fuel Co. began preparing the
project years ago, establishing a team with Shenhua Group and
Ningxia Coal Industry Group. They are partnering with Sasol Ltd. of
South Africa to construct the facility.
3. Capital Airport Expansion Takes Off
The expansion of the Beijing Capital International Airport began
on March 28, 2004, part of the city's preparations for the 2008
Olympic Games. It includes construction of a third runway, a third
terminal building, a cargo zone and some auxiliary communication,
water and oil supply projects. The project, covering an area of
1,480 hectares, will cost 19.5 billion yuan (US$2.3 billion) and be
completed by 2007.
The enlarged airport will be able to accommodate 60 million
passengers and 1.8 million tons of cargo, with 500,000 arrivals a
year, the transport volume predicted for the year 2015.
The contracts include earthworks and drainage at three key
sub-projects: the T3B terminal building, a communication center and
a runway.
A team comprising Dutch airport planners Naco BV, architects
Foster and Partners and engineers Arup won the bid to build the new
terminal building. The building will feature quick transfer time,
an automated, high-speed luggage sorting and transfer system and an
advanced information system.
4. Pubugou Hydropower Station Begins
Construction
On March 30, the Pubugou hydropower station broke ground
alongside the Dadu River in southwestern Sichuan Province, a
significant move in China's development of its western region.
Located in Hanyuan County, the station is the largest water
conservancy project in Sichuan, with an installed capacity of 3.3
million kilowatts. It will annually generate 14.6 billion
kilowatt-hours of electricity. Construction is scheduled to take
eight years and seven month to complete.
The project includes a reservoir for power generation, flood
control and silt blocking. It involves a large number of resident
relocations, complicated geology and a narrow construction site,
making it a hard nut to crack for developing resources on the Dadu
River.
5. Guangdong LNG Import Project Launched
On April 30, the China National Offshore Oil Corporation (CNOOC), BP -- the
world's largest oil company -- and the Guangdong government signed
a commercial contract on liquefied natural gas (LNG) on April 30.
It marked the official launch of the Guangdong LNG import project
and a milestone in the implementation of China's pilot LNG imports
from Australia.
With a total investment of 29.5 billion yuan, the first phase of
the project involves the construction of an LNG import terminal,
trunk line system, four gas power stations, an oil-to-gas power
plant, and gas supply project for four cities in the Pearl River
Delta and two Hong Kong LNG users. It will be completed in
2006.?
6. First Domestically Made Commercial Nuke Power Station
Completed
On May 3, the No. 2 generating unit of the second stage of the
Qinshan Nuclear Power Plant formally went into commercial
operation. The No. 1 and No. 2 generating units of the first large
power station for commercial use designed, built, managed and
operated by the Chinese were already in operation. The station
stands out as one of notable landmarks in the progress of China's
nuclear power construction, by which China has made the leap from
producing small prototype nuclear stations to large commercial
ones.
Construction of the Qinshan power plant was a key project of the
state's Eighth Five-Year Plan (1992-97). Work on the main part of
the project began on June 2, 1996. The installed capacity includes
two 600,000-kilowatt nuclear power generators, costing 14.8 billion
yuan (US$1.8 billion), with a designed operating life of 40 years.
A total of 47 of the 55 key large pieces of equipment so far
completed were domestically made.
The No. 1 generating unit went into operation on April 15, 2002,
47 days ahead of schedule, and has maintained safe, stable and
reliable operation. The No. 2 generating unit was synchronized with
two power grids in March 11 this year and began generating
electricity.
7. Laxiwa Hydropower Station Project Granted
Authorization
In June, the State Council approved the largest hydroelectric
project in the northwest, Laxiwa Hydropower Station. Located on the
main trunk of the Yellow River of Qinghai
Province at the juncture of Guide County and Guinan counties,
the power station has an installed capacity of 4.2 million
kilowatts and an annual average generated energy of 10.2 billion
kilowatts. Total project investment is 14.8 billion yuan (US$1.8
billion).
The damming of the riverbed was completed on January 9, 2004 and
the first generating unit is expected to go into operation in 2008.
The key structures include a concrete hyperbolic arch dam and
underground water diversion generating system, with the height of
dam reaching 250 meters. The power station will become the core of
the northwest power network and will contribute to the west-to-east
electricity transmission plan.
8. CNOOC Undertakes China's Largest Oil Refining
Project
On August 3, the China National Offshore Oil Corporation (CNOOC)
received the government green light for its South China Sea
petrochemical refining project, a major part of CNOOC's effort to
become a comprehensive international energy corporation.
Located in the western South China Sea petrochemical ethylene
project in Huizhou, Guangdong Province, the CNOOC project involves
investment of 16.7 billion yuan (US$20.2 billion). Processing 12
million tons of high acid content crude oil annually, it will be
one of the country's largest oil refineries. Construction is
scheduled to begin at the end of 2005 and the plant to go into
operation in 2008.
When it is complete, the refinery will provide materials for
South China Sea petrochemical ethylene project. By cross-providing
materials and sharing facilities, the two plants will be mutually
complementary, reducing costs and raising the company's overall
profitability.
9. Crude/Refined Oil Pipeline Project Construction Under
Way
In September, construction of the crude and refined oil pipeline
in the northwest region formally began. An 8.8-kilometer trial
section was constructed in Shanshan County, Xinjiang Uygur
Autonomous Region, opening a new line for oil transport in the
region.
The project includes two main lines and seven branch lines, with
the line from Shanshan to Lanzhou, capital of Gansu Province,
stretching 1,550 kilometers. It will be capable of transporting up
to 20 million tons of crude oil from the Tarim, Tuha and Beijiang
oilfields.
The refined oil pipeline stretches 1,840 kilometers from Urumqi
to Lanzhou, with a designed capacity of 10 million tons. It is
scheduled to go into operation at the end of 2005. The crude oil
pipeline will be completed in 2006.
Total pipeline length is 3,986 kilometers, stretching across 25
Xinjiang and Gansu counties.
The project, with the largest designed capacity, longest
distance and highest pressure in the country, was designed and is
being built by the China National Petroleum Corporation with a
total investment of 14.6 billion yuan (US$17.6 billion).
The construction of the pipeline will form a strategic west-east
energy supply corridor.
10. West-to-east Natural Gas Pipeline Begins
Operating
At 9:00 AM on October 1, China's National Day, natural gas
started pumping through the huge west-to-east pipeline, sending
fuel from the Tarim and Changqing gas fields in western Xinjiang
Uygur Autonomous Region and Shaanxi Provinces to Shanghai.
Construction of the 4,000-kilometer-long pipeline began on July
4, 2002, and cost more than 140 billion yuan (US$16.9 billion). It
will transmit 12 billion cubic meters of gas a year. The pipeline
traverses Xinjiang, Gansu, Ningxia, Shaanxi, Shanxi, Henan, Anhui,
Jiangsu, Shanghai and Zhejiang. The completion of the project will
boost the development of Xinjiang, adjust the energy structure of
the Yangtze River Delta area, and help to reduce air pollution.
(China Investment, translated by Guo Xiaohong and Li
Jingrong for China.org.cn January 5, 2005)